Reports until 16:18, Friday 13 June 2014
LHO General
gerardo.moreno@LIGO.ORG - posted 16:18, Friday 13 June 2014 (12360)
Operation Summary

- 8:30 am Filiberto and Aaron to Y-End, to retrieve equipment for use at X-End.
- 8:34 am Corey to the CS VEA, continue work on HAM6.
- 9:25 am Filiberto, Aaron and Vanessa to X-End, continue work with AA/AI chassis.
- 9:35 am Margot to the CS VEA, West bay area work.
- 9:56 am Dale and camera crew to CS VEA, film around West bay and HAM6.
- 10:23 am Cyrus to Y-End, computer work.<--- Done by 11:00 am.
- 10:31 am Thomas to CS VEA, computer work channel fix.
- 11:06 am Dave from CS-CR, DAQ reboot.
- 11:09 am Andres to CS VEA, retrieve item for assembly.
- 11:10 am Dave from CS-CR, ISCEY code restart, succesful.
- 12:23 pm Dave and Jim to Y-End, AI chassis investigation.--->Then to X-Mid for weather station work---->Then to X-End for more Weather work.
- 2:16 pm Jim returning to X-End for more weather work.