Reports until 08:40, Tuesday 17 June 2014
corey.gray@LIGO.ORG -
posted 08:40, Tuesday 17 June 2014 (12386)
Morning Installation Meeting Minutes
-
Jason checking position on ITMx
-
Viewport inspections: Margot documented the TCS ones
-
HAM6 work continues (i.e. Tip Tilt work)
-
HAM4/5--script work yesterday by Hugh, nothing pressing
-
PSL: flow sensor issue (hope to swap), working in H2 enclosure in afternoon,
-
ISC work in racks hope to be completed today
-
Glitchy TMS at end station investigation
-
software watchdog ham4/5 work?
-
Apollo: staging building work on containers
-
Possible HAM4 septum being removed for Hartman alignment
-
Staging: torquing plates together, & cleaning containers
-
cpb: help loading into alignment jig---> will go on this morning with Apollo help
-
BSI ISI #3 Testing continues (hopefully in can at end of the week)
-
Maintenance: Rebolt doing exterior work at kitchen
-
Introduced some new SURF students