H1 General
jim.warner@LIGO.ORG - posted 10:37, Wednesday 18 June 2014 (12406)
Morning meeting summary
-Troubles with ITMX HEPI position, IAS found 3-6mm height errror, will try releasing HEPI stops to see if it returns

-HAM6 OFI/OMC? in chamber is done, ISI needs rebalanced, Robert has measurement to do before unlocking

-HAM4 septum coming out soon, so doors need to come off, TVo working on oplev

-Richard working on ESD feedthrus bsc1

-Gerardo doing viewport survey, lho drawings incomplete, so we are copying llo's layout

-HAM2/HAM3 ISS work coming up

-CPB is ready to balance,

-Apollo moving storage containers into high bay, drilling/cleaning

-NSF Review next week, mostly LVEA and control room