BSC3 HEPI needs to be moved to account for the ITMX height discrepancy Jason will make a final measurement of the ITMX position first SUS is missing payload which will need to be accounted for before the HEPI move bolts have been broken on HAM3 a full cleaning has been done on HAM3, a partial cleaning has been done on HAM2 Travis will remove mobility experiment equipment from the HAM3 west door plan to pull HAM2, HAM3 doors on Monday hold putting doors on HAM6 until next week Robert will be going into HAM6 again today laser work finished on H1 PSL frequency servo investigations to be done planned work in the H2 PSL enclosure Gerardo looking for washers to finish CPB assembly Quad install ongoing in the staging building Scotty cleaning storage can