Reports until 16:07, Monday 23 June 2014
H1 General
jeffrey.bartlett@LIGO.ORG - posted 16:07, Monday 23 June 2014 (12455)
Ops Summary
Day Shift Summary
LVEA Laser Safe 

09:00 Gerardo & Joe – Inspect viewports at HAM2 and HAM3
09:00 Hugh – Disconnect BSC3 HEPI 
09:20 Mike L – SURF tour through LVEA
09:30 Jason – Alignment work at ITMX
09:35 Jeff – Adding dust monitors at HAM2 and HAM3
09:45 Apollo & Jeff – Removing doors on HAM2 and HAM3
13:10 Hugh – Working on ITMX move
13:15 Jeff – Remove witness optics & 4” wafer from HAM2
13:45 Calum & Kate - Remove witness optic and 4" wafre from HAM3
13:52 KingSoft on site working on RO filter 
15:00 Travis – General SUS cleanup in the LVEA
15:05 Dave – Reboot SUS-TMSY for hardware watch dogs
15:00 Dave – Restart the DAC