Reports until 09:54, Tuesday 24 June 2014
corey.gray@LIGO.ORG -
posted 09:54, Tuesday 24 June 2014 (12461)
Morning Installation Meeting Minutes
-
BSC3: 25% of Actuators installed. Will use all of today to continue Actuator Work (Hugh & Greg)
-
HAM2: Need Hazard ASAP to continue work (which will take most of the day). Will run in pseudo Laser Hazard in that barriers will be set up in LVEA to allow Laser Safe in areas away from Laser Hazard work at HAM2. Witness plates removed from HAM2/3.
-
HAM6: Needs cabling attention (when we go back in-chamber). Doors will be tacked on.
-
Beer Garden: Bubba/Apollo working on cleanroom
-
NSF Tour 2-3:15