Reports until 12:00, Friday 27 June 2014
LHO General
justin.bergman@LIGO.ORG - posted 12:00, Friday 27 June 2014 (12467)
ops

Morning Shift 0800-1200 (Corey covering afternoon)

838 – HAM2 setup (Corey and Matt H)

849 – Thomas, Vern, Eric Gustafson doing OpLev survey in corner

      station, following by end stations

902 – Aaron to EX for cable pull (with Manny)

903 – Arnaud beginning measurements at ITMX…should take half

      hour

905 – Matt Heintze and Janeen walkabout in LVEA

930 – Jeff/Andres/Calum/Kate to EX for surveys in preparation  

      for EX vent

1035 – Thomas transitioning End-X to laser HAZARD

1038 – Jeff + Andres foiling and modifying airflows around

       IMC chambers in LVEA

1051 – Jason investigating a rubbing issue on ITMX