travis.sadecki@LIGO.ORG - posted 16:57, Thursday 26 June 2014 (12503)
Alignment of ITMx complete

J. Oberling, A. Pele, myself

Alignment of both M0 and R0 of ITMx have been completed, at least until someone tells us otherwise.  Pitch adjusters have been locked down and all levels of OSEMs tuned to medium-fine.  Stay tuned for alignment values and TF results.