Morning Installation Meeting Minutes

HAM5 SR3:  magnets found, osems to replace, lock up sus until HAM5 isi balanced.  Most morning locking and BOSEM adjust

BSC3:  rebalanced BSC3 & locked ISI for SUS (ACB swung back)

BSC1 (Travis):  checked ESD cables (some issue), coarse PIT work complete & ready for IAS check, spool out & ready for IAS (will take ~day for set up), really want to determine if a HEPI translation will be needed, because this would be a major schedule hit

EX Vent Prep:  Laser Hazard at EX, Sheila staged for QPD work, EX first cleaning complete (2nd cleaning Fri or Mon), Doors off on Tues, 1st week:  ISC & PCal 2nd week

HAM4 TF:  tripped last night, so will want to run 8hr TF (after Apollo noisy work):  avoid noisy work near HAM4

Output Arm Oplevs:  ready for HAM4/5 retroreflection

Viewport Inspection work brought up with chambers being closed soon.

Business:

 

Comments related to this report
jeffrey.kissel@LIGO.ORG - 10:02, Thursday 10 July 2014 (12689)
Richard is also to install Bias filter for ESD drive at EndX, see
E1400296, T1400406, and D1400192.