HAM5 SR3: magnets found, osems to replace, lock up sus until HAM5 isi balanced. Most morning locking and BOSEM adjust
BSC3: rebalanced BSC3 & locked ISI for SUS (ACB swung back)
BSC1 (Travis): checked ESD cables (some issue), coarse PIT work complete & ready for IAS check, spool out & ready for IAS (will take ~day for set up), really want to determine if a HEPI translation will be needed, because this would be a major schedule hit
EX Vent Prep: Laser Hazard at EX, Sheila staged for QPD work, EX first cleaning complete (2nd cleaning Fri or Mon), Doors off on Tues, 1st week: ISC & PCal 2nd week
HAM4 TF: tripped last night, so will want to run 8hr TF (after Apollo noisy work): avoid noisy work near HAM4
Output Arm Oplevs: ready for HAM4/5 retroreflection
Viewport Inspection work brought up with chambers being closed soon.