LHO General
Link
corey.gray@LIGO.ORG -
posted 16:01, Monday 14 July 2014
(12729)
Ops DAY Summary
9:00 Nathan beginning laser work in Optics Lab----->Dick will work with Nathan after 4pm
9:05 Justin heading to both end stations
9:08 EX vent beginning (starting with closing GV20), around 10:30 getting ready to vent--->vented by 11:30
9:16 Removing SRM First Contact (Betsy)
9:20 Locking HAM4 HEPI (Hugh)
9:22 Film crew heading to LVEA (Dale)
9:30
EX Laser SAFE
(Justin)
9:38 Unlocking ITMx & assist with other SUS work (Travis)
10:01
EY transitioned to Laser HAZARD
(Justin)
10:50 Film crew heading to beer garden
10:50
LVEA partial Laser HAZARD
(Justin)
10:55 SR Alignment check (Kissel)
11:01 ITMy IAS work (Jason)
12:04 EX Dust Monitor software work (Jim)
12:53 EY hepi work (Hugh)
1:20pm SR Alignment check completed--->will transition to LVEA laser SAFE
2:00 HAM2 ground loop checks (Filiberto/Andres)
2:09 PCal crew staging/touring EX
2:26 PEM Crew heading to EX to calibrate accelerometers
2:48 Inspecting HAM4/5 optics (Calum/Kate/Nicole)
EX now has (2) Dust Monitors for the EX vent. They are currently NOT connected to the Alarm Handler
3:31 Mode measurements of the OFI by Kissel begins
3:35 Crash phone rung. Only received beeps. No messages...went to dial tone after a 30sec of beeping.
LVEA trasition to Laser SAFE in the afternoon