corey.gray@LIGO.ORG - posted 08:51, Tuesday 15 July 2014 (12748)
Morning Installation Meeting Minutes
SR CHECKOUT (beam reflected off ITM, back through BS, and then through OFI & SRs): ITMx COMPLETED yesterday. ITMy is next and will work on getting there today.
SR3 OSEM work this morning (Jeff/Andres)
Laser HAZARD in ENTIRE LVEA when Jeff/Andres are done at HAM5
EX: vented, crew cleaning, give time for dust to settle, west door removal
EX ISC: check alignment, disable hepi/lock isi, fix pitch by moving masses, start QPD work
EX PCal: Alignment check, window work
EY: deionizer work begins (Rai)
EY cabling/software work
MAINTENANCE: RCG-2.9 Channel Monitoring upgrade at EY
MAINTENANCE: Move autoburt to new server (cyrus)
MAINTENANCE: EX dust monitor work (Jim)
MAINTENANCE: EY test channel monitoring after RCG upgrade. Will restart SUS, ISI, & HEPI models
MAINTENANCE: cp2 liquid nitrogen
DetChar F2F today/tomorrow
BUSINESS: If you received an email from Stella at Caltech be sure to respond promptly!