Reports until 08:43, Monday 21 July 2014
LHO General
patrick.thomas@LIGO.ORG - posted 08:43, Monday 21 July 2014 (12887)
Installation meeting notes
HAM2: Apply first contact, check cables into ISS array
HAM5: Check seismic, clean chamber, pull first contact, run spectrum, close doors
ITMY: Reaction chain alignment
BSC3: Check issues with first contact
end X: PCAL alignment
end Y: Installation of hardware for illuminators, laser noise eater

Install doors on HAM4 and HAM5