BSC1:
Installation and alignment work on ACB
Final IAS check on ITMY
Mitch doing prep work for ACB installation
Filiberto testing the photo diodes
BSC2/BSC3:
Jim BSC2 problem are fixed and TFs are good
Jim is testing BSC3
SUS ready for final close out activities
TCS alignment needs to be checked
End-X:
Will try to close BSC9 this week
LLO crew working on close out prep and cleaning
HAM6:
Plan to open on Tuesday or Wednesday
Electrical:
Cable checkout at HAM6
Prep work for high voltage work for PSL
Gerardo:
Viewport readiness survey