Reports until 08:37, Friday 01 August 2014
corey.gray@LIGO.ORG -
posted 08:37, Friday 01 August 2014 (13135)
Morning Installation Meeting Minutes
-
Will most likely start pumping down Mon (instead of today)
-
Ymanifold spool---installing this morning
-
HAM5 door removal after Spool (to remove irises on SUS--a quick 15min job) & re-install
-
On Mon make sure there are no other gotchas like these irises before pump down
-
BSC2/1 First Contact work and sealing up BSC1
-
viewports work by Gerardo
-
HAM6: Koji & alignment start next week
-
bugzilla: aaai chasis work at all bldgs
-
kills switches for lasers & high voltage work