H2 PSL installation

The H2 diode room back wall (the LVEA wall) was painted and doors were installed in the diode and chiller rooms. More panels put up in the acoustic enclosure and anteroom. Perforated panels were also installed in the anteroom, to allow for airflow.

Dust levels are good.