Reports until 15:54, Monday 04 August 2014
H1 General
jeffrey.bartlett@LIGO.ORG - posted 15:54, Monday 04 August 2014 (13201)
Ops Summary

LVEA laser safe

09:00 – FSS out of lock. Lowered the FSS resonance threshold to 0.3 from 0.4. Peter King will look into PSL alignment.   
09:15 Nathan – Working in the optics lab
09:58 Greg – At BSC1 area working on laser barriers for CO2 laser alignment
10:01 Travis – Working on mobility experiment at HAM3
10:06 Betsy – General post chamber close cleanup in the LVEA
10:13 Gerardo – Working on viewport survey at BSC1/BSC2 area
10:55 Jim – Recycle mid-X weather station software
11:12 Peter – Going into H1-PSL enclosure to tweak ISS alignment/power loss
12:00 Power cycle restart of the camera monitor computer in the control room.  
12:42 Kiwamu & Dave – Kiwamu update and restart LSC model. Dave restart DAQ
13:00 Bubba – End-Y working on deionizer installation
13:27 Bubba – Drilling bolt holes in floor at End-Y
13:47 Gerardo – Viewport survey in LVEA
13:52 Allister – At TCS-X to examine optics
14:10 Karen – Reported the emergency lights are on in the End-Y VEA
14:37 Doug & Jason – Working at the ITM-X manifold 
14:52 Jeff & crew – At End-X 
14:55 Alarm on corner station chiller pump #3. Pump tripped off. Informed John W. 
15:25 Summer students – PEM work at End-X