BSC1 and 3 gatevalve work in progress The extra viewport on BSC2 will be left in place IOT2 table to be moved to west side of HAM2 The north door will be pulled on HAM6 for ISI rebalancing wipe down and particle assessment beforehand Pumping vertex by noon HAM6: placing of fast shutter component today, remainder of work requires beam Peter K. is checking alignment on PSL table TCS: Started bonding polarizer Start work on X arm table after lunch, request for laser hazard in the afternoon ITMX optical lever work in the morning EE work in racks by HAM6 Hugh will be removing the ameristat at HAM4 Rai W. here to work on mirror charging experiment at end Y end Y will be transitioned to laser safe tiltmeter experiment underway at end X Kiwamu updating and restarting the ASC realtime model Praxair delivery to mid Y upgrade of conlog