Apollo installing viewport gatevalves on H1 BSC chambers in LVEA for ionizer equipment 09:03 Nathan starting unattended laser work in the optics lab 09:12 Hugh to HAM4 to remove ameristat and unlock HEPI 09:18 end Y transitioned to laser safe 09:32 Jeff B. and Andres to HAM6, contamination control check 09:41 Travis checking on mobility experiment on west door of HAM3 09:46 Jim B. to check on SEI IOP (unexpected shutdown at 8:41) 09:47 Betsy picking up equipment in LVEA 10:13 Dave and Jim B. restarting end Y SEI, will take down end Y ISC and SUS (on same Dolphin network) 10:16 Hugh done unlocking HEPI 10:39 Dave and Jim B. restarted the mid X weather station 10:56 Sheila to IOT2L, if it has been moved into place will install light pipes 11:00 Bubba to end X to retrieve part for door removal 11:00 Jordan, Paul and Sudarsham to Y1 beam tube enclosure, accelerometer measurements 11:08 Jason and Doug to begin alignment of ITMX optical lever, Arnaud to put ITMX mirror into nominal position 11:18 SnoValley to see John W. 11:34 Paradise water delivery 11:34 starting HAM6 door removal 11:43 Peter K. to end Y to take pictures through viewport 12:03 Krishna, Eric and Jeff K. to end X to work on BRS 13:08 Christina to end X and end Y to install magnetometers 13:12 Aaron to start drilling in the old H1 PSL chiller room (WP 4777) 13:39 Paul and Jordan to end X for PEM measurements 13:57 Dan and Koji to HAM6 to install fast shutter 14:17 Gerardo, Rai and Kyle working on ionizer experiment at end Y 15:43 Fire department investigating trouble panel alarm at mid Y 16:45 Nathan supervised by Dick G. in optics lab Maintenance tasks: PSL chiller filled yesterday, left alone reset HEPI overflow counters for HAM3, BS. John W. confirmed work was done regarding this alog. I set HVE-MY:Y5_246BTORR.HIHI back to 5e-08.