Morning Installation Meeting Minutes
laser safe--->BS Oplev work in morn
laser hazard at ~10am
HAM6/ISCT6 alignment work
LVEA pumping stalled: HAM2 annulur still needs to be done (need to torque down HAM1 doors)
ETMy: back to low pressure. May have a broken ESD channel (will investigate); will need Richard due to High Voltage
EX: doesn't look like it's pumping down normally
Tiltmeter: tightening up and sealing mini chamber today
EY: May require a 3rd Discharge test
Bring in (1 of 3) empty storage container from high bay in the morning (Apollo)
EY B&K hammering (Tim Mcdonald)
H2 enclosure work: PD Arrays (Peter King)
Fire Dept here today
Couple of quads moved to 3ifo storage in LVEA