Reports until 08:27, Monday 11 August 2014
corey.gray@LIGO.ORG -
posted 08:27, Monday 11 August 2014 (13324)
Morning Installation Meeting Minutes
-
laser safe--->BS Oplev work in morn
-
laser hazard at ~10am
-
HAM6/ISCT6 alignment work
-
LVEA pumping stalled: HAM2 annulur still needs to be done (need to torque down HAM1 doors)
-
ETMy: back to low pressure. May have a broken ESD channel (will investigate); will need Richard due to High Voltage
-
EX: doesn't look like it's pumping down normally
-
Tiltmeter: tightening up and sealing mini chamber today
-
EY: May require a 3rd Discharge test
-
Bring in (1 of 3) empty storage container from high bay in the morning (Apollo)
-
EY B&K hammering (Tim Mcdonald)
-
H2 enclosure work: PD Arrays (Peter King)
-
Fire Dept here today
-
Couple of quads moved to 3ifo storage in LVEA