Reports until 17:45, Thursday 01 September 2011
X1 SUS
jeffrey.bartlett@LIGO.ORG - posted 17:45, Thursday 01 September 2011 (1335)
Move Fold Mirror Y to LVEA
Team SUS - Betsy B. Travis S., Andres R., and Jeff B.

Today team SUS removed the Fold Mirror (FMY) from the mechanical test stand in the staging building and transported it to the LVEA. It was craned over the beam tube it is now sitting just outside the BSC/ISI cleanroom. Tomorrow we plan to weigh it and mate it to the BSC/ISI.  