Reports until 08:44, Tuesday 12 August 2014
corey.gray@LIGO.ORG -
posted 08:44, Tuesday 12 August 2014 (13352)
Morning Installation Meeting Minutes
-
Oplevs: start HAM triples today? organizing/cleaning parts
-
Discussion about the LVEA "major leaker" at HAM4 & how this can affect upcoming work. Vent possibly Thurs, which means roughing Fri & possibly weekend.
-
Discussion about HAM6 alignment and also cable clean-up & ISI balancing which will also need to be done afterward.
-
EX: Tiltmeter Chamber sealed up & pumping (Krishna)
-
EY: discussion about ETMy discharge test
-
Property Auditor from CIT on-site
-
Maintenance: rcg2.8.5 build models (so changes will be in effect until after power outage), MSR battery swap, liquid nitrogen at EY