Ops Shift Summary
12:00 – Power is back On. CDs recovery process ongoing
13:25 - Fire Department on site (Maintenance) 
13:45 - Heading to End X to power-cycling electronics- Filiberto
13:45 - Heading to End Y to power-cycling electronics- Aaron
13:48 – 15:35 Going into the LVEA (B-K Hammering) – Tim/Jeff K.
14:03 - Transitioning the LVEA to Laser SAFE – Richard
16:00- CDs recovery process continues ...