Reports until 16:57, Thursday 14 August 2014
LHO VE
kyle.ryan@LIGO.ORG - posted 16:57, Thursday 14 August 2014 (13411)
Venting YBM+Vertex+XBM (at request of others to "re-clock" HAM5/6 septum viewport)
Verbal approvals from Mike L., John W. and Andres R. as I was unable to access eform -> I will replace PT180B, PT120B and PT170B tomorrow while John and others re-clock the HAM5/6 septum viewport.  

NOTE: I tested the three new CC gauges that will be installed on an aux. cart and using PT114B's cable.