Reports until 16:50, Tuesday 19 August 2014
H1 IOO
kiwamu.izumi@LIGO.ORG - posted 16:50, Tuesday 19 August 2014 (13496)
IOT2R table is back in position

Keita, Kiwamu (WorkPermit 4806)

We placed the IOT2R table back in place (i.e. East side of HAM2). We have re-installed the light pipe that connects the lower left viewport of HAM2's east side to the table. The lexan guard of this particular viewport was then removed.

There was some mess on the optical table of IOT2R because of the PRC length measurement. We need to clean them up at some point. Also the GigEs on the table need the interior ethernet cables and feedthrough patch panels. They probably will be useful. The attached is a picture of the IOT2R after we placed it.

Images attached to this report