edmond.merilh@LIGO.ORG - posted 08:47, Friday 22 August 2014 (13552)
Morning Meeting Summary

In attendance: Fred, Vern, Koji, Sigg, Krishna, Worden, Jason, Patrick, Warner, Kissel, Sudarshian?, Arnaud, Kuwami, Gerardo, Sheila, Fil Alexas

OpLev - HAMs 2&3 complete

HAM6 -cabling completed. ISI will be unlocked for J Kissel to run TF. Jim will run TF as well and Koji will attempt to get OMC locked today so that doors can begin to be reinstalled on Monday. North door will be first. Checking for ground loops needs to be done.

TiltMeter at End-X -complete. Communication regarding activities at End-X needs to be addressed. ie, technical cleaning crew frequency. Possibly some signage at the VEA door was mentioned.

End-Y -Measurements taken during green light exposure revealed that charging is NOT being caused by green LASER. The next step will be to investigate ION pump effects.

Visitors next week: Nic Smith will be here 8/26 through 9/10