Reports until 08:39, Thursday 28 August 2014
LHO General
patrick.thomas@LIGO.ORG - posted 08:39, Thursday 28 August 2014 (13634)
Installation meeting notes
Jason to calibrate the optical lever on SR3
Peter to work on the photodiode array in the H2 PSL enclosure
Jim W. running transfer functions on the ITMX ISI. Should finish around 9:30 am.
Filiberto may run cables to the table at HAM6
Kyle will restart pumping at HAM6
Hugh may investigate previous issues with starting HEPI at end Y
Richard may install new HEPI switches