Reports until 18:17, Thursday 08 September 2011
H2 General
jonathan.berliner@LIGO.ORG - posted 18:17, Thursday 08 September 2011 (1369)
Thursday Ops Log

H1's Arms are now Full Open through the End Stations for Squeezer Work

- Lower 3/5's of SUS quad were coming off today, with Calum's crew from Caltech joining
- MX: BSC cleanroom frame moved or preparing to be moved to LVEA
- EX: BSC5 setting
- MY: OpLev work by Eric Black
- EY: ICC of dome in BSC6, HEPI fluid pumping in BSC6
- OSB Doors locked at 6:00pm

- H2:PSL - work on roof

- TCS crew from Caltech arrives to work on H1:TCS-ITMY (Cheryl/Aidan supervising)

- Delivery: Mount's Lock and Key arrives for work at CS (Ski supervising)

- Patrick revising dust monitor code, restarting h0epics1