Reports until 16:25, Thursday 18 September 2014
LHO VE
kyle.ryan@LIGO.ORG - posted 16:25, Thursday 18 September 2014 (14018)
~1545 hrs. local -> Started X2 pressure accumulation data collection
Taking RGA data as the pressure in the X2 Beam Tube module increases following the closing of GV15 (removal of hydrogen pump) -> Expect increasing pressure values indicated by PT345B, PT346B, PT523B and PT524B during test period (testing done on Monday) -> Pressures indicated by these gauges aren't to exceed 5 x 10-7 torr during test period