Reports until 20:34, Monday 19 September 2011
LHO General
patrick.thomas@LIGO.ORG - posted 20:34, Monday 19 September 2011 (1427)
Ops Shift Summary
Cyrus working on paging system
Filiberto extended the dust monitor power and RS485 lines near the new H2 PSL enclosure.
Fire department well testing
Electrical inspector on site
Ski working on air handler system

Activities listed on the white board:
LVEA:
PSL diode / chiller room
SUS / SEI test
squeezer / H1 restore
triage clean storage
welding setup
ICC @ HAM 7,8
HEPI Welding HAM 9

EX:
BSC 5 set, pier set

MY:
oplev test

EY:
ICC @ BSC 6
RGA @ BSC 10
Transmon assy
HEPI Station Run

Plots of > .5 micron dust counts attached. Note relatively high levels at location 7 (near previous location of H2 electronic racks). The dust monitor at location 1 in the LVEA (ISCT 4) has dropped out. There are also some drop outs in the data for the counts in the LVEA from when Filiberto was working on the system. 
Non-image files attached to this report