Reports until 10:06, Monday 06 October 2014
H1 General
jeffrey.bartlett@LIGO.ORG - posted 10:06, Monday 06 October 2014 (14309)
08:30 Meeting Minutes
Richard:   Pulling power and camera cables along the input arm.
	       Working on PCal chassis at both end stations
	       Ken installing receptacles for vacuum pumps in LVEA and VEAs

Gerardo:   Testing optical path of 3IFO OFI in H2 enclosure

Corey: Taking photos of ISC tables
	    Bagging parts in cleanroom by Ham2-3

Betsy: Working on 3IFO Quad builds in LVEA west bay.