H2 AOS
jeffrey.bartlett@LIGO.ORG - posted 17:25, Tuesday 20 September 2011 - last comment - 17:59, Tuesday 20 September 2011(1429)
TMS Suspension moved to Y End
This afternoon the TMS upper suspension was transported to the Y End Station. It has been mated to the Bosch tubing test stand for final assembly and alignment. 
Comments related to this report
keita.kawabe@LIGO.ORG - 17:59, Tuesday 20 September 2011 (1431)
We needed to use full size dog clamps for attaching the suspension frame to the Bosch frame as the top plate was too thick for the low profile ones. 

Some Wire clamps are in the clean/bake, they'll come out tomorrow.

Clean transport box for the suspension structure is still in the EY lab. It will be transported back to the staging building tomorrow.
Images attached to this comment