Displaying report 1-1 of 1.
Reports until 06:46, Tuesday 07 October 2014
H1 PSL (PSL)
richard.savage@LIGO.ORG - posted 06:46, Tuesday 07 October 2014 (14327)
H1 PSL FSS path maintenance
PeterK RickS

We are about to go out to the Laser Area Enclosure early today to swap out the suspect AOM in the FSS optical path to the reference cavity, peak up the alignment, lock down mounts, etc. in an effort to reduce the alignment drifts we have been observing almost since the system was installed (see work permit).
Displaying report 1-1 of 1.