Reports until 16:52, Tuesday 21 October 2014
LHO General
patrick.thomas@LIGO.ORG - posted 16:52, Tuesday 21 October 2014 (14539)
Ops Summary
08:28 - 08:53 cdsfs0 down
08:56 Joe G. to LVEA to retrieve PCAL viewport protector from shelf
09:02 Aaron to pull cables for PCAL (WP 4896)
09:03 Filiberto to end X and end Y to pull cables for HEPI pressure sensors (WP 4905)
09:04 Ed to end X and end Y to check ESD AI chassis filter board versions (WP 4902)
09:11 Jeff B. and Andres looking for parts in optics lab
09:14 John hard-closing GV18 for PCAL viewport protector replacement work (WP 4903)
09:17 Joe G. and Rick to end Y to replace PCAL viewport protector (WP 4903)
09:28 Hugh troubleshooting sensor problem at ITMX (WP 4899)
09:31 Sudarshan and Shivaraj to end X to work on PCAL cabling
09:36 Jeff K. making changes to end X ISI and HEPI models, restarting models
09:40 Contractor to see Bubba and John
09:54 Jeff B. and Andres done in optics lab
10:01 Jeff K. done with model changes and restarts, ready for DAQ restart
10:13 Joe G. and Rick done replacing PCAL viewport protector
10:22 Richard to LVEA to trace HEPI pressure sensor cables
10:29 Unifirst delivery
10:29 Cyrus working on h1broadcast0, restarting
10:31 Kyle reopening GV18
10:35 DAQ restart, error from duplicate channels in Beckhoff
10:58 Richard routing HEPI pressure sensor cables
11:00 Ed done, replaced both boards
11:00 Hugh back to BSC2
11:23 Cyrus done work on h1broadcast0
11:24 Richard done routing HEPI pressure sensor cables
11:44 Daniel done making Beckhoff changes (WP 4904)
11:48 Hugh done in LVEA
13:09 Kyle and John running purge air compressor at end Y (WP 4907)
13:09 Doug and Jason retrieving parts from LVEA
13:42 Doug and Jason done retrieving parts
13:44 Doug and Jason to end Y to realign optical lever
14:08 Ed to SUS test stand, checking UIM chassis
14:20 Doug and Jason done aligning end Y optical lever
15:18 Shivaraj and Patrick updating PCAL Beckhoff code at end X
15:20 Kyle and John done running purge air compressor at end Y