Morning Meeting Summary
Work permits update.
Pcal group:to work on both systems the rest of the week, at both end stations, including laser activity.
OpLev group: setting up assembly area, and assembly of damping components to be installed on piers. Jeff K. to work on OpLev calibration.
Report of Y-End station seismometer out, part of the LHO PEM system, Filiberto to look into it.
SEI group: commissioning of sei-systems.