Reports until 09:53, Monday 17 November 2014
LHO General
edmond.merilh@LIGO.ORG - posted 09:53, Monday 17 November 2014 (15097)
Morning Meeting Summary

SEI - plans to do some upgrading/standardiing on Tuesday (maintenence day). Otherwise, standing by to assist with commsissioners.

SUS - plans to work in W bay in the mornings for the entire week

PSL - working on issues with ISS second loop. Also, issues with an apparent 30% power fluctuation that may have something to do with an errant reflection??

3IFO - gearing up for SUS baffle build. Working in VPW to clean up for Contractors

CDS - X-end work - power up and checks

           Y-end work - cabling

Facilities - bring palette jack from MX to staging building. Working to maintain temperatures everywhere. Apolllo may be here this week. Their work will include sawing asphalt which will be conidered invasive.                        operators should be kept informed as to all activities of this nature.

Op Lev - re-alignment work of SR3 (work permit #4946). This will neccessitate transitioning to full LASER SAFE at some point.

Commissioning schedule to remain the same; 12:00 cutoff for noisy work in VEAs unless otherwise granted

grouting in the LVEA discussed as imminent in the not-so-distant future.