Commissioning calendar for next 2 weeks
Here is the list of commissioning task for the next 7-14 days:

Locking team:
  1. Lock DRMI with ALS arm cavity offset.
  2. Common hand-off to transmitted power.
  3. Lock interferometer.
  4. Improve automatic search for red resonance.
  5. Check RF power on 2f detectors.
Modecleaner team:
  1. Investigate long-term alignment stability of mode cleaner.
  2. Investigate back reflected/scattered light.
Alignment team:
  1. Make EY green WFS work again.
  2. Install EX green WFS auto-centering hardware.
  3. Commission an arm alignment controls topology which can be used for initial alignment.
  4. Integrate green WFS into initial alignment.
RF:
  1. Make an assessment of RF cross talk into the IMC AOM.
  2. Investigate EMI radiation by the VCOs and the fixed frequency OCXO.