Reports until 16:00, Friday 21 November 2014
LHO General
patrick.thomas@LIGO.ORG - posted 16:00, Friday 21 November 2014 (15237)
Ops Summary
07:03 Karen cleaning in LVEA
08:11 Jeff B. and Andres to LVEA west bay
08:23 Jeff B. and Andres back
08:41 Jeff B. and Bubba to LVEA to look at container
08:43 Filiberto and Aaron to end Y to work on PEM
08:52 Cris checking mid and end stations for cleaning
08:56 Jeff B. and Bubba moving storage containers in LVEA (no craning)
08:57 Travis to LVEA teststand to work on suspension
09:21 Keita to end X to work on green WFS
09:32 Jeff B. and Bubba done
09:32 Travis done
10:10 Cris done
10:40 Jeff B. turned on dust monitor 10 (under cleanroom for 3IFO work)
11:02 Gerardo to H2 PSL laser enclosure to work on OFI
11:09 Cris dropping off frocks at end X
11:22 Bubba taking U.S. Linen to mid and end stations (not in VEAs)
11:25 Keita done
12:04 Hugh and Jim W. checking boards at ITMX
12:13 Filiberto and Aaron done (also labeled cables at end X)
12:25 Hugh and Jim W. done
12:25 Gerardo done
13:48 Corey looking for cables in squeezer bay
14:06 Corey done
15:02 Gerardo back to H2 PSL laser enclosure to continue work on OFI