jonathan.berliner@LIGO.ORG - posted 19:45, Monday 10 October 2011 - last comment - 12:09, Tuesday 11 October 2011(1526)
Monday (Columbus Day) Ops Log
PSL - 808nm light generated today. Vacuuming done in area. Preparations for 35W eLIGO laser startup. State electrical inspector visited PSL enclosure. Richard was working on access system.
SUS - Placed main chain on reaction chain.
EY - TMS work with Craig Conley and Jesse. Epoxy complete.
Rai - preparation for hydrocarbon test at EY. Negotiations ongoing with Squeezers about timing closing of GV18.
H1 - Remained locked throughout most of today's activity. LVEA returned to laser hazard by evening.
Tours - Whitman College (including LVEA tour with MikeL) and another group led by Dale and FredR.
Comments related to this report
michael.rodruck@LIGO.ORG - 12:09, Tuesday 11 October 2011 (1536)
No 808nm light yet, we plan on doing that today (Tuesday)