LHO Corner Station HEPI Pump Controller Updated

Finally got rid of the tired database and now have all the new useful channels.  Take a look at the new pump controller medm screen.  There are still a number of cables to run but all the ports available are at least in use now and database junk has been discarded.  We still need to modify the board to power the amplifier for the remote pressure sensors at BSC2; we'll try to knock that out next week.

Attached is a shot of the new controller screen.

Images attached to this report