Reports until 15:03, Wednesday 17 December 2014
H1 COC
vernon.sandberg@LIGO.ORG - posted 15:03, Wednesday 17 December 2014 - last comment - 15:08, Wednesday 17 December 2014(15685)
Schedule for BSC10 Vent and ETMY Cleaning

Approved work to be done:


  1.   Cleaning and assessment of ETMY HR surface
  2.   Replacement of EY ESD vacuum feethrough connector assembly
  3.   P-Cal alignment

Thursday, Dec. 11


Friday, Dec 12


Monday, Dec 15

After Chamber Vent Following E1400430
1: Disconnect external (air side) ESD cable from feed thru.
2: Install flat surface with Vacuum Foil on it near Flange for a work
surface.
3: Remove ESD feed thru flange  Gerardo
4: IF enough cable exist cut the cables from the connector on the inside.
    IF not enough cable disconnect cable
    disassemble connector then remove connector ends.
5: Crimp new pin on to cables.
6: Verify with SUS which pin is connected to which part of ESD.
7: Make up connector with new pins in proper order D1400177 V2
8: Secure new connector to new feed thru.
9: Install Flange on Vacuum chamber.  Gerardo
10: Connect new external cabling to feed thru
11: Ensure no one is near optic!!!  High Pot connector ~ 700V DC  If it
doesn't pass.  Stop and investigate.
12: Make up external cables to field current limiting resistor box.

Tuesday, Dec. 16


Wednesday, Dec. 17

The last step is at the time and discretion of the Vacuum crew.

Comments related to this report
vernon.sandberg@LIGO.ORG - 15:08, Wednesday 17 December 2014 (15686)

Decision flow diagram from E1400472, drawing by D. Coyne

Images attached to this comment