Reports until 16:24, Friday 14 October 2011
H2 SEI
jim.warner@LIGO.ORG - posted 16:24, Friday 14 October 2011 (1570)
BSC 8 Rebalanced
(Radkins, Robinson, Warner)

BSC 8 had Stage2 ballast mass removed and was floated and balanced. Some minor adjustments were required to Stage1 trim mass, and multiple CPS's needed regapped, mostly on Stage2. The system was left in a locked state for SUS cabling work, but should be otherwise fully functional. The weight distribution on Stage2 is ugly, but will need be revisited after the cartridge install because all of the keel mass will be removed to facilitate the lift.