Reports until 16:07, Thursday 18 December 2014
LHO VE
kyle.ryan@LIGO.ORG - posted 16:07, Thursday 18 December 2014 (15722)
Vacuum system related activities
Kyle, Gerardo, Bubba -> ~0930 hrs. local -> Removed BSC9 West door 

Kyle -> ~1350 hrs. local -> Started pumping BSC10 annulus 

Kyle -> ~1500 hrs. local -> Decoupled pump cart from HAM1/HAM2 annulus (Climbed on and around HAM1 and HAM2)