Morning meeting minutes
Z/RZ seb ongoing
Changing CD at HAM3
Sus 3IFO storage
Recovery from RCG update ongoing
Schnupp measurements
Possible loose mirrors in REFL path in vaccuum
Opening X-arm gate valves, annulus ion pump needs to be repaired
Safety meeting this afternoon
Z/RZ on filtering on BSC-ISI testing ongoing
Changing coil drivers at HAM3 ISI
Sus 3IFO storage activities in the VLEA
Recovery from RCG update ongoing
Schnupp measurements ongoing
Possible loose mirrors in REFL path in vaccuum on HAM2
Opening X-arm gate valves, annulus ion pump on BSC3 needs to be repaired
Safety meeting this afternoon
 