Reports until 16:06, Monday 26 January 2015
H1 General
edmond.merilh@LIGO.ORG - posted 16:06, Monday 26 January 2015 (16266)
Morning Meeting Summary

10:00AM Guidline in effect for Commissioning starting today.

SEI - work on installing blend filters from LLO on HAM3

SUS -  working on SDF

CDS - video work around HAM2. Microphone problem is fixed.

3IFO - no work in te LVEA this week and will be postponed for some time.

Corey moving things in Squeezer bay.

Beam Tube Cleaning to resume today on X arm - Apollo on site.

Sudarshan mentioned a desire to work on P-Cal at EX and EY

Nutsinee reporting to LHO for operator position

Thomas Abbott visiting. Will be helping with Drift monitor/ P-Cal etc