Reports until 17:03, Thursday 27 October 2011
H2 FMP
jodi.fauver@LIGO.ORG - posted 17:03, Thursday 27 October 2011 (1633)
BSC-4/HAM-9 ICC
The crew did not get into BSC-4 until after lunch due to a couple of factors. However, first vacuum, bellows clean-up, and support tube fiber removal were completed today. Since tomorrow is a short day (due to aLIGO 1st anniversary lunch), we'll work on the dome and should be able to finish it. We'll start wipe down next week.