The test stand cleanroom was moved back into the VEA from the middle bay after the test stand re-build was completed. The work space and garbing/staging cleanrooms were moved into their nominal positions for the BSC-6 cartridge install. The test stand and work space cleanrooms are ready to be nested to clear the test stand for the ISI placement tomorrow.