H2 SEI
hugh.radkins@LIGO.ORG - posted 10:17, Monday 07 November 2011 (1670)
BSC ISI Shifted on Test Stand
The ISI was rehung (moved clean room out of the way.  Lift gear was reattached, ISI unbolted from MTS and lifted.  Unit was shift East (toward corner station) 7" and lowered back to MTS.  This shift accommodates the attachment of hte TransMon.  It does make working on the East side of the ISI quite tight...won't be too fun but we'll manage.
Thanks JimW & Apollo (Scott Mick & Mark)