To accommodate the remaining 3IFO work before the end of project there will be extended noise hours until the end of March. Each Tuesday from 08:00 to 16:00 will be open for noisy work around the site. Floor access after 10:00 on the other days may be allowed with commissioner’s approval. Seismic - Working on HEPI pump commissioning Suspensions – Running transfer functions on ETMX and SR2 Vacuum – Preparing to start pumping at HAM1. Will coordinate with Daniel before starting work Electrical – Will be moving racks from End-Y to the H2 electronics building in the near future Safety Meeting – John reviewed the melted plug/receptacle extension cord problem from last week. The portable transformers will be shut down, and extension cords removed as the LVEA and VEAs are cleaned up for the ER run. Each subsystem should be looking into shutting down unused equipment and removing any extension cords wherever possible.