Reports until 16:20, Wednesday 18 February 2015
H1 AOS
jeffrey.bartlett@LIGO.ORG - posted 16:20, Wednesday 18 February 2015 (16799)
Ops Day Shift Summary

LVEA: Laser Hazard
Observation Bit: Commissioning  

08:21 Betsy – Running TFs on ETMX and SR2
08:23 Corey – 3IFO work in H2 Squeezer bay
08:25 Filiberto – Pulling cables at HAM6
08:49 Mitch – 3IFO work in West Bay
08:55 Cris – Cleaning at Mid-X
08:55 Karen – Cleaning at End-Y
09:03 Mitch – Out of LVEA
09:15 Travis – Going into the LVEA looking for tooling 
09:22 Doug – Going to optics cabinet near H1-PSL enclosure
09:35 Travis – Out of the LVEA
09:39 Corey – Going to End-Y
09:41 Apollo – Starting up A/C units for DCS
09:55 Richard – Swap IR Spool (X arm) camera zoom lens
10:20 Jodi & Travis – Going to Mid-X and Mid-Y to look for parts
10:24 Elli – Going to X-Arm Spool 
10:52 Dan – Giving a tour of LVEA for students   
10:53 Jodi & Travis – Back from the Mid stations
10:55 King Soft on site to take water samples
11:10 Richard – Out of LVEA
13:07 Filiberto & Ed – Going to End-Y to remove 3IFO power supplies 
14:25 Corey – Going into the LVEA
14:31 Corey – Out of the LVEA
15:00 Guardian training in OSB large conference room